Abbey Junior School

Classroom remodelling at The Abbey Junior School

Sector: Education
Client: The Abbey
Value range: Under £500k

The project involved the refurbishment and remodelling of existing classrooms on the first-floor level, along with new mechanical and electrical services.

Scope of work

Structural Modifications:

  • Demolition of two load-bearing walls on the first floor, utilizing temporary structural needle propping per the site-specific temporary works design.
  • Installation of new steel beams and new acoustic stud partitions to alter the classroom layout.

Interior Enhancements:

  • Classrooms received new plaster ceiling finishes, fire precautions, bespoke skirting, and plaster coving to match existing designs.
  • Upgraded floor finishes, wash hand basins, sink units, noticeboards, window film, roller blinds, vision panels, and decorative finishes.
  • Installation of new bespoke teacher wall systems.

Ground Floor Upgrades:

  • Cavity wall construction to block existing external doors and install new external windows and an aluminium door set.
  • Incorporation of a new level threshold access ramp to meet DDA requirements.

Mechanical and Electrical Upgrades:

  • Stripped out the existing boiler house and installed a new boiler, control system, and heating facilities.
  • New mechanical installations included radiators, heating pipework, air cooling units, and new waste connections to sink units.
  • Electrical installations included new LED lighting, emergency lighting, fire detection systems, small power, and AV connections.

The new classroom refurbishments at The Abbey significantly enhance the school’s educational facilities, providing a modern, accessible, and energy-efficient environment for both students and staff.