Contract Award: Cantley Park 1000 663 Morris & Blunt

Contract Award: Cantley Park

Morris & Blunt Ltd are pleased to announce the recent contract award of an internal and external refurbishment project at Cantley Park, Wokingham. Planned works include internal alterations and reconfiguration of the existing sports pavilion…

read more
Progress Update at: The Willink School 2560 1920 Morris & Blunt

Progress Update at: The Willink School

This month at The Willink School, all structural steelwork has been installed. The suspended concrete floor planks have now been installed together with the completion of the concrete staircase. The Sub-base, ground floor slab, and…

read more
Progress Update at: Down Grange Sports Arena 2560 1167 Morris & Blunt

Progress Update at: Down Grange Sports Arena

This month has seen the completion of the bottom car park, receiving its surface finish and white lining, opening it up for use to the public whilst works are carried out within the top car…

read more
Progress Update at: The Post Barn – Wedding Venue 2048 1536 Morris & Blunt

Progress Update at: The Post Barn – Wedding Venue

The Post Barn has had all its roofing works complete this month, along with the mechanical plant now in place on the flat roof. Inside the building, installations have continued for the first fix of…

read more
Progress Update at: Crowthorne Baptist Church 1095 704 Morris & Blunt

Progress Update at: Crowthorne Baptist Church

Crowthorne Church has received its second and final fix of mechanical, electrical, and carpentry fittings this month, along with the further installation of both external windows and doors throughout the building. The flat roof has…

read more
Completion at: National Trust – Yew Tree Cottage 2016 1512 Morris & Blunt

Completion at: National Trust – Yew Tree Cottage

This month has seen the successful completion and handover at our Project at Yew Tree Cottage on behalf of the National Trust. Works have included the full replacement of bespoke roof and hanging tiles, insulation…

read more
Progress Update at: Foundry College 970 592 Morris & Blunt

Progress Update at: Foundry College

This month has seen the development of internal timber-framed walling, external cladding,  first and second fix carpentry, as well as electrical and plumbing fixings. Furthermore, screeding, plasterboard, suspended ceilings, and decorations have all been applied…

read more
Progress Update at: Down Grange Sports Arena 2560 1173 Morris & Blunt

Progress Update at: Down Grange Sports Arena

This month the erection of the steel frame has been completed and has also received roof cladding, with further cladding components currently being present on-site, whilst the structure is currently receiving its brick and blockwork…

read more
Progress Update at: The Post Barn – Wedding Venue 1960 1470 Morris & Blunt

Progress Update at: The Post Barn – Wedding Venue

The Post Barn is currently receiving a range of internal fit-out works. Plastering is underway in both the large and small barns as well as to the WCs, with ceilings being complete in some of…

read more
Progress Update at: National Trust – Yew Tree Cottage 2049 1536 Morris & Blunt

Progress Update at: National Trust – Yew Tree Cottage

Following an Engineers assessment to the extent of the works required, refurbishment and repairs have begun to the roof. With the roof made structurally sound, along with new board and batten coverings, it is now…