This month at The Post Barn external works have been carried out, including the retaining walls nearing completion with only the ramp wall remaining, as well as storm and aco drains having been installed around the barn and courtyard. In the Courtyard, external power runs are currently under construction ready for external lighting, whilst the stoning of the ground around the courtyard and building has been carried out ready for further hard surface finishes.
Internally, plastering and floor tiling is complete throughout the main barn areas, whilst further tiling in the being carried out within both sets of bathrooms. The metal frame ceiling has now been complete, with acoustics panel installation to follow shortly upon completion of decoration. Further works currently underway include final door hangings, ironmongery installation, sanitary ware fittings, installation of the mezzanine handrail, and the final application of vinyl flooring.